- VARIOUS ACTIVITIES IN SUPPORT OF THE ASL 2 TO 2 TECHNICAL DEPARTMENT OF LOGISTICS
- Provision of technical data sheets in order to support the renovation plan and long-term maintenance of the various buildings.
- Technical and graphical depiction of the buildings’ outer shells.
- Mapping of outer shells’ deterioration.
- Brief assessment of operations.
- FIRE PREVENTION PROJECT
- Final works of completion: arrangement of fire prevention compartments and upgrading fire escape routes of the various buildings.
Client: A.S.L. TO 2 (ex A.S.L. 3)
GRUGLIASCO (TO) - PRELIMINARY DRAFT OF RESIDENTIAL HEALTH CARE "VILLA OF CATS - POLO 2"
Preliminary design concerning the recovery of the former Grugliasco Psychiatric Hospital’s Pavilion "D" in order to construct a nursing home of 64 beds divided into two groups of 15 beds: "Alzheimer" and "Complex," and two cores of 17 beds
Renovation of Rationalist 1930s building with the objective of bio-sustainability and energy innovation in a park
Client: ASL 3 Collegno – Pinerolo (TO)

AMEDEO DI SAVOIA HOSPITAL DISTRICT
- MAKING NEW PAVILION FOR INFECTIOUS DISEASES AND NEW MEDICAL PLATE TECHNOLOGY
- Revision of preliminary, final and executive pavilion "L" and the medical plate technology "I" and local technical general area
- VARIOUS ACTIVITIES TO SUPPORT THE TECHNICAL DEPARTMENT OF LOGISTICS TO ASL 2
- General Programme of reorganization of the district: provision of graphic documentation
- New technical areas (centre for medical gas - electric cabin - central water supply – in-house fire department): preliminary architectural infill; project to obtain the Construction Permit, Landscaping Report, intention of obtaining the opinion of the Superintendent
- New grade-level car park: Landscaping Report
- Measures for the adaptation of the regulatory and functional "Pavilion A - Office Building" project to obtain the opinion of the Superintendent
- FIRE PREVENTION MEASURES
- Final project work in various buildings in the district:
- Completion of fire preventative compartments and upgrading fire escape routes
- Production and reserve water network
- Construction upgrades and reorganisation of sewage works as a reserve fire safety measure
Client: A.S.L. TO 2 (ex A.S.L. 3)

RESTRUCTURING OF THE CASTLE TO BE USED AS RESIDENCES FOR THE ELDERLY (RSA, RA, RAF) FOR A TOTAL OF 124 BEDS
Feasibility study
Urban plan of recovery
Preliminary, final and executive design
Project management
PARTIAL RENOVATION AND EXPANSION OF THE CASTLE FARM APPLIANCES FOR THE IMPLEMENTATION OF A NUMBER OF RESIDENTIAL CARE HOMES, HEALTH-CARE CENTRES, RISS FOR A TOTAL OF 92 BEDS AND 36 DAY-USERS
Preliminary and final design
Client: Company Montaldo Castle LTD